Wichita water statistics update

The Wichita ASR water project had a relatively good month in June, but has not been producing water at the projected rate or design capacity.

An important part of Wichita’s water supply infrastructure is the Aquifer Storage and Recovery program, or ASR. This is a program whereby water is taken from the Little Arkansas River, treated, and injected in the Equus Beds aquifer. That water is then available in the future as is other Equus Beds water.

With a cost so far of $247 million, the city believes that ASR is a proven technology that will provide water and drought protection for many years. Last year the city recommended that voters approve $250 million for its expansion, to be paid for by a sales tax. Voters rejected the tax.

Gallons of Water Recharged Through Recharge Basins and Wells during Wichita ASR Phase II, cumulative.
Gallons of Water Recharged Through Recharge Basins and Wells during Wichita ASR Phase II, cumulative.
According to city documents, the original capacity of the ASR phase II project to process water and pump it into the ground (the “recharge” process) was given as “Expected volume: 30 MGD for 120 days.” That translates to 3,600,000,000 (3.6 billion or 3,600 million) gallons per year. ASR phase II was completed in 2011.

At a city council workshop in April 2014, Director of Public Works and Utilities Alan King briefed the council on the history of ASR, mentioning the original belief that ASR would recharge 11,000 acre feet of water per year. But he gave a new estimate for production, telling the council that “What we’re finding is, we’re thinking we’re going to actually get 5,800 acre feet. Somewhere close to half of the original estimates.” The new estimate translates to 1,889,935,800 (1.9 billion) gallons per year.

Gallons of Water Recharged Through Recharge Basins and Wells during Wichita ASR Phase II, cumulative since July 2013.
Gallons of Water Recharged Through Recharge Basins and Wells during Wichita ASR Phase II, cumulative since July 2013.
Based on experience, the city has produced a revised estimate of ASR production capability. What has been the actual experience of ASR? The U.S. Geological Survey has ASR figures available here. I’ve gathered the data and performed an analysis. (Click charts for larger versions.)

I’ve produced a chart of the cumulative production of the Wichita ASR project compared with the original projections and the lower revised projections. The lines for projections rise smoothly, although it is expected that actual production is not smooth. The second phase of ASR was completed sometime in 2011, but no water was produced and recharged that year. So I started this chart with January 2012.

2013 was a drought year, so to present ASR in the best possible light, I’ve prepared a chart starting in July 2013. That was when it started raining heavily, and data from USGS shows that the flow in the Little Arkansas River was much greater. Still, the ASR project is not keeping up with projections, even after goals were lowered.

Gallons of Water Recharged Through Recharge Basins and Wells during Wichita ASR phase II.
Gallons of Water Recharged Through Recharge Basins and Wells during Wichita ASR phase II.
On the chart of monthly production, the horizontal line represents the revised annual production projection expressed as a constant amount each month. This even rate of production is not likely, as rainfall and river flow varies. In the three years that ASR phase II has been in production, that monthly target been exceeded in two months.

In June 2015, the ASR project recharged 205 million gallons of water. Its design capacity is 30 million gallons per day, so the work done in June represents seven days of design capacity. The ASR project is able to draw from the Little Arkansas River when the flow is above 30 cfs. As can be seen in the chart of the flow of the river, the flow was above this level for the entire month.

Flow of the Little Arkansas River at Valley Center. The ASR project is able to draw from the river when the flow is above 30 cfs at this measurement station.
Flow of the Little Arkansas River at Valley Center. The ASR project is able to draw from the river when the flow is above 30 cfs at this measurement station.
At one time the city was proud enough of the ASR project that it maintained an informative website at wichitawaterproject.org. That site no longer exists.
At one time the city was proud enough of the ASR project that it maintained an informative website at wichitawaterproject.org. That site no longer exists.

Comments

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.