Naftzger Park cost rising, and we’re not to talk about it

on

The cost of the Naftzger Park makeover is rising, will be paid for with borrowed funds, and possibly handled without public discussion.

The cost of the Naftzger Park project in downtown Wichita is rising, according to an item the Wichita City Council will consider at its Tuesday February 5, 2019 meeting. According to city documents, an additional $85,000 is needed for stormwater retention, a function the former pond provided.

This seems like a major oversight in the original project plans. The city has regulations regarding stormwater retention that private sector developers must follow. Didn’t any city planners consider these regulations as the project was planned? Didn’t any council member or bureaucrat look at the plans and wonder about stormwater drainage? Wasn’t there a highly-regarded architect designing the park? What about TGC Development, the developer of the surrounding property, to whom the city effectively outsourced the development of Naftzger Park? The construction manager?

The extra cost is proposed to come from savings realized in another nearby project. That requires a waiver of policy, according to the agenda: “Staff requested waiver of City Council Policy No. 2 regarding the use of projects savings to allow this transfer of funds.”

On top of that, this money will be borrowed. An accompanying resolution (number 19-048) provides the authorization: “Section 2. Project Financing. All or a portion of the costs of the Project, interest on financing and administrative and financing costs shall be financed with the proceeds of general obligation bonds of the City.”

Borrowing this money, even though it is a small amount, is a significant public policy issue. The city decided to use tax increment financing (TIF) to pay for this project. City officials pitch this as a method of financing that costs the general public nothing, as the TIF bonds are repaid from a project’s future property taxes.

In this case, as the surrounding development by TGC starts to pay higher property taxes, these taxes would be used to pay for Naftzger Park. (Never mind who pays for the public services the development will consume.)

But now, some expenses of the project have been shifted away from TIF to the general city.

The equitable way of handling this is to charge this expense to the TIF district. Either that, or to the responsible parties whose oversight, we now see, was lacking.

By the way, this item is on the consent agenda, meaning there will be no discussion unless a city council member requests the item to be “pulled” for discussion and a potentially separate vote. (A consent agenda is a group of items that are voted on in bulk with a single vote. An item on a consent agenda will be discussed only if a council member requests the item to be “pulled.” If that is done, the item will be discussed. Then it might be withdrawn, voted on by itself, or folded back into the consent agenda with the other items. Generally, consent agenda items are considered by the city to be routine and non-controversial, but that is not always the case.)

Following, an excerpt from the February 5, 2019 city council agenda:

Background: Naftzger Park currently has a small pond that acts as a storm water retention facility during rain events. Proposed improvements to Naftzger Park will eliminate the pond and all available storm retention. The project does not include funding for replacing the retention capacity.

Analysis: With the elimination of the existing pond, underground on-site storage is necessary to prevent a negative impact on the area storm sewer system and the surrounding developments during rain events.

Financial Considerations: Currently, the Stormwater Utility does not have funding available for these improvements. Staff proposes transferring $85,000 in General Obligation bond funding from the Douglas Underpass project. Funding is available for transfer due to underruns of bid items upon project completion and favorable bid pricing. Staff requested waiver of City Council Policy No. 2 regarding the use of projects savings to allow this transfer of funds. The total budget for the stormwater retention facility would be $85,000 and the revised budget for Douglas Underpass would be $2,015,000.

Comments

2 responses to “Naftzger Park cost rising, and we’re not to talk about it”

  1. Robet e culver

    No , of course not it is all about how to keep screwing this city snd the people out of money or to keep the city further in debit , oh and how to keep all the money on west side and downtown instead of spreading it out , the idiots that run this city is all about making them and their friends rich , this is what happens when good old boys keep getting elected.

  2. […] industrial revenue bonds. He has also found himself on the same side as many progressives on the redevelopment of Naftzger Park. Weeks would eventually support Brandon Whipple for mayor because of his concerns about […]

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.